A risk is something that might go wrong; an issue is something that already has. Every project collects issues, and the danger is not the issues themselves but the ones nobody owns. The issue log gives every problem a number, a priority, an owner and a date, and counts how many are still open. The escalation form is for the few issues the team can't solve alone. The decision log records what was decided and why, which ends the "I thought we agreed..." conversations.

Formats
PDF, Word, Excel, ODT, ODS
Paper
US Letter and A4
Fillable
Yes, with totals

Updated November 11, 2026

Filled-in example of the Issue log design
Filled-in example: Issue log.

Choose a design

Pick the design that fits

Issue log - filled-in example

Issue log

ID, date raised, the issue, who raised it, priority, impact, owner, next action, due date, status and date resolved. A 1 in the open column for each unresolved issue lets Excel count the backlog.

OpenDocument: ODT · ODS

Issue report and escalation form - filled-in example

Issue report and escalation form

For an issue that needs a decision above the team: what happened, the impact on scope, time and cost, what the team has tried, the options with pros and cons, the recommendation and the decision needed by when.

OpenDocument: ODT · ODS

Project decision log - filled-in example

Project decision log

Every significant decision with the date, what was decided, the options considered, who decided, the reason and the effect on the plan. Ends arguments about what was agreed.

OpenDocument: ODT · ODS

What is on the page

Issue and impact
What is wrong now and what it affects: a deliverable, a date, the budget, customers. Be specific enough that someone new could understand it.
Priority
High if it blocks the project, medium if there is a workaround, low if it is an annoyance. Agree the definitions so priorities mean the same to everyone.
Owner and next action
One person responsible for getting it resolved, and the very next step with a date, not just "look into it".
Open count
Enter 1 for open and 0 for closed issues; Excel totals the open ones, the number to watch each week.
Decision record
What was decided, the options, who decided, why, and what it changed in the plan.

Running an issue log

Log an issue as soon as someone raises it, with a number, the date and the person who raised it. Agree the priority, assign one owner and write the next action and its due date. Review open issues at every team meeting, starting with the high-priority ones, and close them only when resolved, noting how. Keep closed issues on the log; they are a useful record of what went wrong and how it was fixed. An issue that needs a change to scope, budget or dates becomes a change request. Report the count of open high-priority issues in the weekly status report.

Issues versus risks

A risk is a possible future problem; an issue is a problem that has happened. Risks go on the risk register with a likelihood and a response plan; when a risk happens, it moves to the issue log. Keeping them seperate stops the issue log filling with "what ifs" and keeps the team focused on what needs action now.

When to escalate

Escalate an issue when the team can't solve it within its authority: it needs more money, a change of scope or date, a decision between departments, or help from outside the project. Escalating early isn't a failure; escalating late is. Use the escalation form to make it easy for the sponsor to decide: state the issue and its impact, what has been tried, two or three options with their pros and cons, your recommendation and the date a decision is needed. A sponsor given clear options usually decides in minutes.

Why keep a decision log

Months into a project, few people remember why a choice was made, and decisions get reopened. A short log of each significant decision, with the options considered and the reason, prevents that and helps new team members understand the project. Record decisions from meetings (see the meeting notes template) and from escalations in one place.

Editing the files

The PDFs are fillable. The Excel issue log counts open issues and can be filtered by owner, priority or status. Add columns for category or link issues to tasks on the project task tracker.

Questions

What is a project issue log?

A list of problems that have arisen during a project, each with an ID, description, priority, impact, owner, next action, due date and status.

What is the difference between an issue and a risk?

A risk might happen in the future; an issue has already happened and needs action now.

When should an issue be escalated?

When it needs a decision or resources beyond the team's authority, such as more budget, a scope or date change, or help from another department.

What is a decision log?

A record of significant project decisions with the date, the options considered, who decided, the reason and the effect on the plan.

Does the log count open issues?

Yes. Enter 1 for each open issue and Excel totals them.

How useful was this template?

Tap a star to rate it. Your rating helps other people pick a template.

Comments and questions

Have a question about this template, or an idea to make it better? Leave a comment.

Leave a comment

Comments are checked before they appear, usually within a day or two. Please keep personal details out of your comment.