Free Project Change Request Form: Change Request with Cost and Schedule Impact, Change Log, and a Client Change Order (PDF, Word, Excel)

Changes are normal in any project; unmanaged changes are what blow budgets and deadlines. A change request makes each one a decision instead of a drift: what exactly is changing, why, what it costs in time and money, and who approved it. The change log shows the running total of every change against the original plan. For client work, the change order turns an approved change into a signed amendment of the contract price, so the final invoice holds no surprises.

Formats
PDF, Word, Excel, ODT, ODS
Paper
US Letter and A4
Fillable
Yes, with totals

Updated November 11, 2026

Filled-in example of the Change request with impact analysis design
Filled-in example: Change request with impact analysis.

Choose a design

Pick the design that fits

Change request with impact analysis - filled-in example

Change request with impact analysis

Who is asking, what should change and why, the priority, then the impact on scope, schedule and cost with an itemized estimate that Excel totals, the options considered, and the approval decision.

OpenDocument: ODT · ODS

Change log - filled-in example

Change log

Every change request in one list: number, date, description, who asked, cost and schedule impact, status and decision date. Excel totals the approved extra cost and days against the original budget and finish date.

OpenDocument: ODT · ODS

Client change order - filled-in example

Client change order

For contractors, agencies and freelancers: the original contract, the change described and priced, previous change orders, the new contract total that Excel calculates, the new completion date, and signatures from both sides.

OpenDocument: ODT · ODS

What is on the page

Change requested and reason
What exactly would change and why. A vague request ("make it better") cannot be priced or approved.
Impact
The effect on scope, schedule, quality and other work, and an itemized cost estimate that Excel totals.
Options
Usually at least three: do it now, do it later, do not do it. Often "later" gives most of the benefit with none of the delay.
Change log totals
The approved extra cost and days across all changes, and the budget after changes, compared with the original.
Change order totals
Original contract amount plus previous change orders plus this one gives the new contract total, which both sides sign.

How change control works

Anyone can ask for a change, but only the sponsor or client can approve one, and only after seeing what it costs. The project manager writes the request (or helps the requester write it), works out the impact with the team, lists the options, and takes it to the approver. Every request goes on the change log, approved or not, so there's a record of what was asked and decided. Changes that are approved update the scope statement, the plan and the budget. Small teams can do all of this in a ten-minute conversation, as long as it's written down.

Estimating the impact

Look beyond the obvious work. A new feature needs building, but also testing, documentation, training and sometimes a subscription or a part. Ask whether it pushes the finish date, whether it adds risk, and what other work it delays. In the sample, adding store pickup costs $1,440 and five days; the approved option was to launch on time and add pickup in June which kept the launch date and the full benefit. That kind of choice is only visible when the options are written next to each other.

Change orders on client projects

For agencies, contractors, builders and freelancers, a change order is how extra work gets paid. Describe the change clearly, price it item by item, show the original contract amount and any earlier change orders, and state the new total and the new completion date. Do not start the extra work until the client signs; work done on a verbal "yes" is the most common source of unpaid invoices. Many construction contracts and some state laws set specific rules for change orders, so check yours. Invoice the change with the next milestone or as agreed in the payment terms. The estimate template helps price larger changes.

Editing the files

The PDFs are fillable, and the change order in Word can carry your logo and contract terms. Excel totals the cost estimate, the change log and the new contract total. Number change requests and change orders in sequence (CR-01, CO-01) and keep them with the contract.

Questions

What is a project change request?

A written request to change a project's scope, schedule, cost or quality, with the reason, the impact and the approval decision.

What is the difference between a change request and a change order?

A change request asks for and analyses a change; a change order is the signed agreement that amends a contract, usually its price and completion date.

Who approves project changes?

The project sponsor or client, or a change board on larger projects. The project manager prepares the request and impact analysis.

Should I start work before a change order is signed?

No. Start extra work only after the client signs, so the scope and price are agreed.

Does the form calculate the cost?

Yes. The Excel versions total the cost estimate, the change log and the new contract total.

How useful was this template?

Tap a star to rate it. Your rating helps other people pick a template.

Comments and questions

Have a question about this template, or an idea to make it better? Leave a comment.

Leave a comment

Comments are checked before they appear, usually within a day or two. Please keep personal details out of your comment.